How Illinois summers and winters change a pour, and what to ask for when you order.

Concrete can be poured in almost any month in Illinois. What changes with the season is how fast it sets, how it has to be protected, and what we put in the mix.

Cold weather

Cold slows concrete down. It takes longer to set and longer to gain strength, and concrete that freezes in its first days can be permanently weakened.

What we do at the plant

What you do at the job

Hot weather

Heat speeds concrete up. It stiffens faster, the surface dries before it can be finished, and cracks from drying are more likely. Wind and low humidity make all of this worse.

What we do at the plant

What you do at the job

Rain

Light rain after the surface has set does little harm. Heavy rain on fresh concrete washes cement off the surface and weakens it. Keep plastic sheeting on site, and if rain looks likely, call dispatch early about moving the pour.

There may be a charge for late cancellations.

Questions? Call dispatch.

A dispatcher can answer anything on this page for your job and your pour date.

Call dispatch · (815) 942-4344

Open Monday to Friday, 6 a.m. to 5 p.m. (4 p.m. in winter); Saturday by arrangement.

Want a price first? Request a quote →

More guides

Call dispatch · (815) 942-4344