A foundation is usually three pours with three different jobs to do. The mix is not the same for each, so tell the dispatcher which one you are ordering.
The mix, pour by pour
- Footings. Footings are not exposed to freezing and thawing once they are covered, so they are normally poured with concrete that has no entrained air.
- Foundation walls. Air entrainment makes wall concrete more cohesive, and it protects the parts of the wall that are exposed to weather.
- Basement and garage floors. Interior slabs that will not freeze are poured without entrained air. That matters if the floor will be finished with a troweling machine: air-entrained concrete can blister under a power trowel. For a slab placed over a vapor barrier, ask about a reduced-air mix, which slows bleeding.
Foundations and flatwork are normally placed at a 4 to 5 inch slump. If you need the concrete to flow more easily, ask for a water reducer when you order.
Reinforcing steel and cold weather
If the pour contains rebar and you want a faster set in cold weather, ask for a non-chloride accelerator. Calcium chloride must not be used with reinforcing steel.
Getting it into the forms
Walls and basement floors are often out of reach of the truck’s chute. Our sister company Central Illinois Conveying runs boom pumps, line pumps and belt conveyors. See pumping and conveying, or ask the dispatcher to set it up when you order. Foundations are normally poured with our standard 3/4 inch stone. A mix with 3/8 inch pea gravel or limestone chips is available on request.
What to tell dispatch
- Which pour it is: footing, wall or floor.
- The yardage, or the dimensions. Our concrete calculator handles slabs, footings and columns.
- How it will be placed: chute, pump or conveyor.
- When you want the first truck, and how fast your crew can take the following ones. Large pours need 24 to 48 hours of notice so we can reserve trucks.
See Ordering & Delivery for unloading time and delivery terms, and Hot and cold weather concrete for winter pours.